BESS Capacity Augmentation

Every battery loses usable energy as it ages, but a storage contract rarely allows the owner to deliver less. A project sold on four hours at a stated megawatt rating must still deliver that energy in year ten. Capacity augmentation is the practice of adding battery capacity during the life of the plant so the contracted energy keeps being met. It is a design decision that has to be made at the start, because it shapes the converter sizing, the site layout and the warranty. This page sits under the Battery Energy Storage Systems hub.

Why augmentation is needed

Usable energy falls with cycling and with time, at a rate that depends on how hard the system is worked, as covered in BESS Ageing vs Duty Cycle. The obligations the plant is paid against, such as a capacity market commitment or an offtake agreement, are fixed. Over time the gap between the two grows, and the owner has to close it by adding capacity or accept penalties or lost revenue.

Overbuild at day one or stage it

There are two broad strategies, and most projects use some mix of them.

  • Overbuilding: install more energy than the contract needs from the start, and let degradation consume the margin. It is simple and avoids later works, but the extra cells are bought, financed and kept at a state of charge from year one. The converter has to be sized so it can still deliver full power when the extra capacity is in use.
  • Staged augmentation: install close to the contracted size and add capacity at planned points. Money is spent later, when cell prices may be lower and the extra energy is actually needed, but the owner takes on works at a live site, a second procurement, and the risk that the chosen product is no longer available.

The balance depends on the cost of capital, expected cell price trends, and how certain the owner is about the degradation rate. Sizing the day-one system with these in mind is the subject of BESS Sizing.

How capacity is added

Capacity can be added as additional racks or containers, or by replacing degraded modules within the existing enclosures. Adding racks to an existing DC bus is the most direct, but it relies on spare space, spare connection points and spare converter capacity being designed in. Plant built with its own converter behind each block of batteries can be extended by adding whole blocks, while a shared converter with a common DC bus is more constrained.[1] The AC-coupled and DC-coupled choice therefore has a long-term effect on how easily the plant can be extended.[2]

Mixing old and new cells

New cells added beside aged ones will differ in capacity, resistance and often in chemistry or format if the original product is no longer made. Putting them in the same series string or the same parallel group lets the weakest cells set the limits, so the usual approach is to keep old and new cells in separate strings, each with its own controls. Even then the BMS and plant controller must handle two groups with different state of health, share power sensibly between them, and report them correctly. Why cells drift apart, and how that limits a pack, is covered in Cell to Cell Variation. The converter needs the headroom to manage the new, higher-capacity mixture without being derated.

Warranty and contract effects

Manufacturer warranties usually assume the original configuration. Adding or replacing equipment may need the supplier’s agreement, a new warranty for the added part, and a clear boundary between what each warranty covers. Some suppliers include a capacity maintenance obligation or an augmentation price in the original contract, which turns the future cost into a known number. How performance guarantees are written is a separate topic, and the finance side of lifetime cost is introduced in The Battery as an Asset.

References

  1. Battery energy storage augmentation: key project considerations, Burns & McDonnell.
  2. AC and DC augmentation in BESS: the differences between the two approaches, Energy-Storage.news.